Waterproofing Solution for Below Ground Masonry Wall.

NCC Version:

2022

Area of NCC Requirements:

Section F Health and Amenity

Part F1 Surface Water Management

Problem:

Client requested that a masonry wall within the laundry area have a Performance Solution completed to allow for part of the wall to be retaining backfill.

Solution:

Performance Solutions Australia assessed the construction method and made small tweaks to the overall building solution to ensure both area's of the NCC were covered and that a Functional Statement be made to show compliance and how the building will not be adversely effected by the wall installation.

Finalised Report:

This included the Brief with stakeholders' signatures, once approved the final Report was created to accompany the Brief with documentation being submitted to the Registered Building Surveyor to make up part of the Building Permit.